As an immediate solution, the TMI Superintendent recommended using a material to fill the damaged areas. The fill product sets up fast and dries quickly. With the owner’s approval, the fill was completed and the TMI Coatings team was able to continue with the flooring project and complete it on schedule. The customer was pleased with the workmanship, safety, cleanliness of the site and his finished floor.
TMI Coatings recently completed a project with stringent time requirements. The deadline of February 21 gave the team less than a week to complete a flooring project, which usually is not a problem. However, when prepping the floor, the TMI Superintendent discovered an area approximately 100 sq. ft. where the cap, which is the top portion of the concrete, was disbonding and eroding severely. With other contractors due to start on the 22nd, there was not time to pour a new floor.

Begin Prep and Repairs
As an immediate solution, the TMI Superintendent recommended using a material to fill the damaged areas. The fill product sets up fast and dries quickly.

Floor Prior to Coating Application
With the owner’s approval, the fill was completed and the TMI Coatings team was able to continue with the flooring project and complete it on schedule. The customer was pleased with the workmanship, safety, cleanliness of the site and his finished floor.

TMI Coatings Team Applying the Floor Coating

Completed TMI Coatings Flooring Project
Call TMI Coatings for your flooring projects and you will receive the same personalized attention to your job.











1 response so far ↓
1 Tweets that mention TMI Coatings Resolves Floor Erosion Problem -- Topsy.com // Mar 25, 2010 at 11:54 pm
[...] This post was mentioned on Twitter by TMI Coatings. TMI Coatings said: TMI Coatings Resolves Floor Erosion Problem http://www.tmicoatingsblog.net/archives/102 http://bit.ly/bbQsPh [...]
Leave a Comment